The Standard: Difference between revisions
Jump to navigation
Jump to search
m (rm {{clear}} causing wrapping issues) |
(image) |
||
Line 4: | Line 4: | ||
#5' easement on the east side of the building for future access | #5' easement on the east side of the building for future access | ||
#Pedestrian access way on the west side of the building | #Pedestrian access way on the west side of the building | ||
#Bicycle parking: internal spaces equal to at least 20% of on-site parking spaces; at least 1 publicly accessible space per 1000sf commercial space.|approval_process=Special Use Permit|acres=2.517 acres|location=853 West Main Street (formerly 853, 855, and 901 W. Main)|use_type=Mixed-Use Apartments & Retail|units_residential=189 units (644 bedrooms)|non_residential=7,000sf commercial (originally 15,530sf)|stories=6|parking=499 spaces (structured)|height=70'|floor_area=345,790 square feet|construction_start=November 2016|construction_complete=August 2018|developer_company=[[Landmark Properties]]}} | #Bicycle parking: internal spaces equal to at least 20% of on-site parking spaces; at least 1 publicly accessible space per 1000sf commercial space.|approval_process=Special Use Permit|acres=2.517 acres|location=853 West Main Street (formerly 853, 855, and 901 W. Main)|use_type=Mixed-Use Apartments & Retail|units_residential=189 units (644 bedrooms)|non_residential=7,000sf commercial (originally 15,530sf)|stories=6|parking=499 spaces (structured)|height=70'|floor_area=345,790 square feet|construction_start=November 2016|construction_complete=August 2018|developer_company=[[Landmark Properties]]|map-image=The Standard 2018-10-12.jpg}} | ||
'''The Standard''' is a six-story apartment building on [[West Main Street]] completed in the summer of 2018. It is built on the site of the former [[Republic Plaza]]. <ref>{{cite web|title=Republic Plaza slated for demolition to clear way for six story building|url=http://www.cvilletomorrow.org/news/article/15684-republic-plaza-demolition/|author=Sean Tubbs|work=|publisher=Charlottesville Tomorrow|location=|publishdate=August 19, 2013|accessdate=August 5, 2014}}</ref> It was developed by [[Landmark Properties]]. | '''The Standard''' is a six-story apartment building on [[West Main Street]] completed in the summer of 2018. It is built on the site of the former [[Republic Plaza]]. <ref>{{cite web|title=Republic Plaza slated for demolition to clear way for six story building|url=http://www.cvilletomorrow.org/news/article/15684-republic-plaza-demolition/|author=Sean Tubbs|work=|publisher=Charlottesville Tomorrow|location=|publishdate=August 19, 2013|accessdate=August 5, 2014}}</ref> It was developed by [[Landmark Properties]]. |
Revision as of 23:10, 18 August 2019
The Standard | ||
---|---|---|
853 West Main Street (formerly 853, 855, and 901 W. Main)
|
||
Use Type | Mixed-Use Apartments & Retail | |
Lot Size | 2.517 acres | |
Gross Floor Area | 345,790 square feet | |
Building Height | 70' | |
Stories | 6 | |
Residential units | 189 units (644 bedrooms) | |
Non-Residential | 7,000sf commercial (originally 15,530sf) | |
Parking | 499 spaces (structured) | |
Development Firm | Landmark Properties | |
Approval Process | Special Use Permit | |
Approval Conditions | Five conditions:
|
|
Date Approved | 2013 | |
Construction Started | November 2016 | |
Construction Completed | August 2018 | |
Application # | SP-13-08-15 |
The Standard is a six-story apartment building on West Main Street completed in the summer of 2018. It is built on the site of the former Republic Plaza. [1] It was developed by Landmark Properties.
The developer's local representative is John Matthews.
Timeline
- August 20, 2013: BAR grants demolition permit for Republic Plaza [2]
- September 10, 2013: Charlottesville Planning Commission holds initial meeting to discuss the project [3][4]
- September 17, 2013: BAR holds review of the project [5]
- October 8, 2013: Planning Commission recommends approval [6][7]
- November 4, 2013: Council approves special use permit [8][9]
- January 2014: BAR grants certificate of appropriateness [10]
- May 2016: BAR amends certificate of appropriateness and develop says construction could begin by the end of the year. [11]
- November 2016: Fences erected around the Republic Plaza in advance of demolition.
- December 2016: Developer makes payment of $665,000 to the Charlottesville Affordable Housing Fund [12]
- January 2018: Developer makes payment of $50,000 to the city for workforce development training [13]
- August 2018: The Standard opens to residents, finishes major construction[14]
- October 3, 2018: A kitchen fire injures 1 and displaces 14.[15]
This article is a stub. You can help cvillepedia by expanding it. |
Construction photos
References
- ↑ Web. Republic Plaza slated for demolition to clear way for six story building, Sean Tubbs, Charlottesville Tomorrow, August 19, 2013, retrieved August 5, 2014.
- ↑ Web. BAR approves demolition for 25-year-old building on West Main, Sean Tubbs, Charlottesville Tomorrow, August 20, 2013, retrieved August 5, 2014.
- ↑ Web. New West Main housing complex critiqued, Charlottesville Tomorrow, September 10, 2013, retrieved August 5, 2014.
- ↑ Web. Charlottesville Planning Commission meeting minutes, .pdf, City of Charlottesville, September 10, 2013.
- ↑ Web. City reviews impacts of more housing for university students on West Main, Sean Tubbs, Charlottesville Tomorrow, September 23, 2013, retrieved August 5, 2014.
- ↑ Web. Commission recommends approval for West Main apartments, Sean Tubbs, Charlottesville Tomorrow, October 13, 2013, retrieved August 5, 2014.
- ↑ Web. Charlottesville Planning Commission meeting minutes, .pdf, City of Charlottesville, October 8, 2013.
- ↑ Web. Council approves second West Main student housing building, Sean Tubbs, Charlottesville Tomorrow, November 5, 2013, retrieved August 5, 2014.
- ↑ Web. Charlottesville City Council meeting minutes, .pdf, Council Chambers, City of Charlottesville, November 4, 2013.
- ↑ Web. January 2014 Charlottesville Board of Architectural Review minutes, Minutes, City of Charlottesville, retrieved October 8, 2017.
- ↑ Web. Six-story West Main apartment project moving forward, Sean Tubbs, Charlottesville Tomorrow, May 17, 2016, retrieved May 18, 2016.
- ↑ Web. Developer of The Standard to pay $665,000 to city housing fund, Sean Tubbs, News Article, Charlottesville Tomorrow, December 5, 2016, retrieved April 22, 2018.
- ↑ Web. Agenda for January 16, 2018 City Council, City of Charlottesville, January 16, 2018, retrieved 2018-10-06.
- ↑ Web. UVA students back for the new semester, Brianna Hamblin, CBS19, August 25, 2018, retrieved 2018-10-06.
- ↑ Web. Fire at The Standard apartment complex displaces 14, Daily Progress, Lee Enterprises, October 4, 2018, retrieved 2018-10-06.