Line 36: Line 36:
*September 8, 2010: The road will come up during the Board of Supervisor's public hearing on the University of Virginia's request to rezone the [[Fontaine Research Park]].
*September 8, 2010: The road will come up during the Board of Supervisor's public hearing on the University of Virginia's request to rezone the [[Fontaine Research Park]].
*August 10, 2011: City Council candidates discuss road at [[Charlottesville City Council candidate forum, 2011 August 10 (2nd)|Fry's Spring Neighborhood association candidate forum]]. <ref>{{cite web|title=City council candidates debate Fontaine-Sunset Connector|url=http://cvilletomorrow.typepad.com/charlottesville_tomorrow_/2011/08/conn.html|author=Sean Tubbs|work=|publisher=Charlottesville Tomorrow|location=|publishdate=August 19, 2011|accessdate=October 14, 2011}}</ref>
*August 10, 2011: City Council candidates discuss road at [[Charlottesville City Council candidate forum, 2011 August 10 (2nd)|Fry's Spring Neighborhood association candidate forum]]. <ref>{{cite web|title=City council candidates debate Fontaine-Sunset Connector|url=http://cvilletomorrow.typepad.com/charlottesville_tomorrow_/2011/08/conn.html|author=Sean Tubbs|work=|publisher=Charlottesville Tomorrow|location=|publishdate=August 19, 2011|accessdate=October 14, 2011}}</ref>
 
*December 18, 2012: 2009-10 traffic modeling suggests that the road might not help as much as once thought<ref>{{cite web|title=Traffic model challenges benefits of Sunset-Fontaine Connector |url=http://www.cvilletomorrow.org/news/article/13697-sunset-fontaine-connector/ |author=Tim Shea |work=|publisher=Charlottesville Tomorrow |location=|publishdate=December 19, 2012 |accessdate=December 20, 2012}}</ref>


==Map==
==Map==

Revision as of 14:53, 20 December 2012


Fontaine/Sunset Connector
Fontaine-sunset.jpg

Planned

Project Overview

Road interconnection between Fontaine Ave and Sunset Avenue/Old Lynchburg Road area in County. Expected alignment traverses the Granger Property and the UVA Fontaine Research Park. Cost includes bridge over railroad tracks.
Cost $12,800,000 (estimate)
Sponsor Albemarle
Next meeting November 15, 2011 Albemarle Planning Commission

Status Update

Part of Area B Study - The County, City and the University of Virginia continue to discuss the road, and most recently[when?] it was a topic of a PACC meeting.

Contact David Benish, Chief of Planning, Albemarle County

The Fontaine/Sunset Connector is a proposed road to connect Fontaine Avenue in Charlottesville with Sunset Avenue/Old Lynchburg Road in Albemarle County.

Project details

The project was one of the recommendations of the Southern Urban Area B Study in September 2004. While the road is still in the conceptual stage, the expected alignment traverses the Granger property and the University of Virginia's Fontaine Research Park. The $12,800,000 project includes a bridge over railroad tracks.

A subdivision plat submitted to Albemarle County's community development department shows that Stribling Holdings LLC will build the portion of the connector on its property. A September 2010 rezoning for the Fontaine Research Park established that the University of Virginia Foundation will set aside land for a portion of the connector road. [1]

Status

Ambox notice.png This article documents a current event. Information may change rapidly as the event progresses.

This project was called for in the Southern Urban Area B Study. Planning is currently[when?] in the conceptual stage. The county, city and UVa are negotiating the alignment for this proposed connector. As such, the primary forum for negotiations is the Planning and Coordination Council. The Thomas Jefferson Planning District Commission is currently studying UVa's preferred alternative of running the road down Stribling Avenue. The study is expected to be ready in time for the November 18, 2010 PACC meeting[2].

The project is currently priority #8 on the County's Six Year Plan for Secondary Roads for Fiscal Year 2009[3]. However, the project is also listed on the MPO's Transportation Improvement Program as an illustrative transportation project, which means it is not likely to begin receiving funding for some time[4].

Project history

  • May 19, 2009: At a PACC meeting, Leonard Sandridge says the University will not pay for off-site improvements as part of a rezoning effort[5]
  • July 16, 2009: At a PACC Tech meeting, County Planner Wayne Cilimberg says Charlottesville and Albemarle County would like the MPO Tech committee to discuss possible alignments for the road[5].
  • September 8, 2010: The road will come up during the Board of Supervisor's public hearing on the University of Virginia's request to rezone the Fontaine Research Park.
  • August 10, 2011: City Council candidates discuss road at Fry's Spring Neighborhood association candidate forum. [6]
  • December 18, 2012: 2009-10 traffic modeling suggests that the road might not help as much as once thought[7]

Map

References

  1. Web. Granger property to be developed by-right; connector road part of plans, Sean Tubbs, Charlottesville Tomorrow, November 15, 2011, retrieved November 15, 2011.
  2. Fitzgerald, Brendan. "C-Ville: UVA - Sunset/Fontaine Connector Gets New Study." C-VILLE Charlottesville's News & Arts Weekly | Charlottesville VA News Music Culture Dining. 31 Aug. 2010. Web. 31 Aug. 2010. <http://www.c-ville.com/index.php?cat=141404064432695&ShowArticle_ID=11803008103673232>.
  3. County's Strategic Priorites for Albemarle County Priority List for Secondary Road Improvements
  4. FY09-12 TRANSPORTATION IMPROVEMENT PROGRAM. Rep. Charlottesville-Albemarle Metropolitan Planning Organization. Web. 13 Oct. 2009. <http://www.tjpdc.org/pdf/TIP/FINAL_%20FY09%20TIP.pdf>
  5. 5.0 5.1 Tubbs, Sean J. "County, City planners seeking updated plans for Fontaine-Sunset Connector; Sandridge says UVA will not contribute to road needs outside research park." Weblog post. Charlottesville Tomorrow News Center. Charlottesville Tomorrow, 17 July 2009. Web. 27 July 2009. <http://cvilletomorrow.typepad.com/charlottesville_tomorrow_/2009/07/fontaine_sunset_news.html>.
  6. Web. City council candidates debate Fontaine-Sunset Connector, Sean Tubbs, Charlottesville Tomorrow, August 19, 2011, retrieved October 14, 2011.
  7. Web. Traffic model challenges benefits of Sunset-Fontaine Connector, Tim Shea, Charlottesville Tomorrow, December 19, 2012, retrieved December 20, 2012.