| cost =$3,000,000 | | cost =$3,000,000 | ||
| sponsor = | | sponsor =VDOT | ||
<!--ABOVE USE: Albemarle, Charlottesville, VDOT --> | <!--ABOVE USE: Albemarle, Charlottesville, VDOT --> | ||
| purpose =Provide greater safety for motorists and others using Route 53. | | purpose =Provide greater safety for motorists and others using Route 53. |
Revision as of 09:27, 8 July 2009
Rt. 53 Buck Island Creek Bridge Replacement | ||
---|---|---|
Completed
|
||
Project Overview
|
| |
Provide greater safety for motorists and others using Route 53.
|
||
Cost | $3,000,000 | |
Sponsor | VDOT | |
Status Update
|
| |
New bridge complete. As of January 12, 2006, demolition of old bridge near completion. |
||
Contact | Jim Utterback, Charlottesville Residency Administrator, Virginia Department of Transportation |