Line 8: | Line 8: | ||
[http://www.cvilletomorrow.org/docs/water/200401-SafeYield.pdf Safe Yield Study] by [[Gannett Fleming]], January 2004 | [http://www.cvilletomorrow.org/docs/water/200401-SafeYield.pdf Safe Yield Study] by [[Gannett Fleming]], January 2004 | ||
* This report documents a safe yield of 13.3 MGD (revised downward in July 2004 report) | * This report documents a [[safe yield]] of 13.3 MGD (revised downward in July 2004 report) | ||
[http://www.cvilletomorrow.org/docs/water/200405-GF-DemandAnalysis.pdf Demand Analysis for the Urban Service Area] by [[Gannett Fleming]], May 2004 | [http://www.cvilletomorrow.org/docs/water/200405-GF-DemandAnalysis.pdf Demand Analysis for the Urban Service Area] by [[Gannett Fleming]], May 2004 | ||
Line 16: | Line 16: | ||
[http://www.cvilletomorrow.org/docs/water/200407-watersupplyalternatives.pdf Water Supply Alternatives Supplemental Evaluation] by [[Gannett Fleming]], July 2004 | [http://www.cvilletomorrow.org/docs/water/200407-watersupplyalternatives.pdf Water Supply Alternatives Supplemental Evaluation] by [[Gannett Fleming]], July 2004 | ||
* This report documents the downward adjustment of current safe yield from 13.3 MGD to 12.8 MGD (2002). | * This report documents the downward adjustment of current [[safe yield]] from 13.3 MGD to 12.8 MGD (2002). | ||
* It projects the safe yield in 2055 to be 8.8 MGD. | * It projects the [[safe yield]] in 2055 to be 8.8 MGD. | ||
* It identifies the goal of finding 9.9 MGD in new water supply (18.7 MGD - 8.8 MGD = 9.9 MGD). | * It identifies the goal of finding 9.9 MGD in new water supply (18.7 MGD - 8.8 MGD = 9.9 MGD). |
Revision as of 15:38, 3 May 2009
Government Studies
Key governmental studies related to the Charlottesville-Albemarle Community Water Supply Plan
Raw Water Supply Demand Analysis by Vanasse Hangen Brustlin, October 1997
- This report recommends planning for water supply demand in 2050 to be between 18 MGD and 21 MGD.
Safe Yield Study by Gannett Fleming, January 2004
- This report documents a safe yield of 13.3 MGD (revised downward in July 2004 report)
Demand Analysis for the Urban Service Area by Gannett Fleming, May 2004
- This report recommends planning for water supply demand in 2055 to be 18.7 MGD with 5% conservation measures.
Water Supply Alternatives Supplemental Evaluation by Gannett Fleming, July 2004
- This report documents the downward adjustment of current safe yield from 13.3 MGD to 12.8 MGD (2002).
- It projects the safe yield in 2055 to be 8.8 MGD.
- It identifies the goal of finding 9.9 MGD in new water supply (18.7 MGD - 8.8 MGD = 9.9 MGD).
Independent Studies
Gahagan & Bryant dredging assessment, May 2008