List of water supply studies: Difference between revisions

From Cvillepedia
Jump to navigation Jump to search
No edit summary
No edit summary
Line 5: Line 5:
[http://www.cvilletomorrow.org/docs/water/200407-watersupplyalternatives.pdf Water Supply Alternatives Supplemental Evaluation] by Gannett Fleming, July 2004
[http://www.cvilletomorrow.org/docs/water/200407-watersupplyalternatives.pdf Water Supply Alternatives Supplemental Evaluation] by Gannett Fleming, July 2004


This report documents the downward adjustment of safe yield (2004) from 13.3 MGD to 12.8 MGD.   
This report documents the downward adjustment of current safe yield from 13.3 MGD to 12.8 MGD (2002).   


It identifies the goal of finding 9.9 MGD in new water supply.
It projects the safe yield in 2055 to be 8.8 MGD.  It estimates the demand in 2055 to be 18.7 MGD.
 
It identifies the goal of finding 9.9 MGD in new water supply (18.7 MGD - 8.8 MGD = 9.9 MGD).

Revision as of 22:13, 22 February 2009

Key studies related to the Charlottesville-Albemarle Community Water Supply

Safe Yield Study by Gannett Fleming, January 2004

Water Supply Alternatives Supplemental Evaluation by Gannett Fleming, July 2004

This report documents the downward adjustment of current safe yield from 13.3 MGD to 12.8 MGD (2002).

It projects the safe yield in 2055 to be 8.8 MGD. It estimates the demand in 2055 to be 18.7 MGD.

It identifies the goal of finding 9.9 MGD in new water supply (18.7 MGD - 8.8 MGD = 9.9 MGD).