The developer, [[Wendell Wood]], received approval for Hollymead Town Center from the Albemarle County [[Board of Supervisors]] in July of 2003<ref>http://cvilletomorrow.typepad.com/charlottesville_tomorrow_/2006/09/htcproffers.html Charlottesville Tomorrow, 8 Jan 2009</ref>. Since then, other sections of the town center have been rezoned, each under different zoning categories.  
The developer, [[Wendell Wood]], received approval for Hollymead Town Center from the Albemarle County [[Board of Supervisors]] in July of 2003<ref>http://cvilletomorrow.typepad.com/charlottesville_tomorrow_/2006/09/htcproffers.html Charlottesville Tomorrow, 8 Jan 2009</ref>. Since then, other sections of the town center have been rezoned, each under different zoning categories.  
===Potential residential build-out===
Hollymead Town Center Area C has a total capacity of 120 dwelling units and 34 {{as of|2011|9|28|alt=have been built}}. <ref name="table6">{{cite web|title=CPA 2013-00001 COMPREHENSIVE PLAN REVISION
Part 2: Trends|url=http://www.albemarle.org/upload/images/forms_center/departments/community_development/forms/PC_Reports/COMP_PLAN_UPDATED_10-11_STAFF_REPORT3.pdf|author=|work=Table 6: Residential Units Approved through Rezonings and Special Use Permits|publisher=County of Albemarle|location=|publishdate=September 28, 2011|accessdate=October 11, 2011}}</ref>




==Timeline==
==Timeline==
*August 6, 2003: Board of Supervisors approves rezoning. <ref name="table6"/>
*January 11, 2011: Albemarle Planning Commission recommends amendment of proffers to change required timing of construction of Meeting Street. Also recommends halving of amount developer must contribute towards transit. <ref name="jan2011-proffers">{{cite web|title=New Kohl’s store still on schedule after Hollymead proffer amendment|url=http://cvilletomorrow.typepad.com/charlottesville_tomorrow_/2011/01/hollymead-proffers.html|author=Sean Tubbs|work=|publisher=Charlottesville Tomorrow|location=|publishdate=January 13, 2011|accessdate=February 1, 2011}}</ref> [http://www.cvilletomorrow.org/docs/20110112-Hollymead-Rezoning.pdf Meeting notes]
*January 11, 2011: Albemarle Planning Commission recommends amendment of proffers to change required timing of construction of Meeting Street. Also recommends halving of amount developer must contribute towards transit. <ref name="jan2011-proffers">{{cite web|title=New Kohl’s store still on schedule after Hollymead proffer amendment|url=http://cvilletomorrow.typepad.com/charlottesville_tomorrow_/2011/01/hollymead-proffers.html|author=Sean Tubbs|work=|publisher=Charlottesville Tomorrow|location=|publishdate=January 13, 2011|accessdate=February 1, 2011}}</ref> [http://www.cvilletomorrow.org/docs/20110112-Hollymead-Rezoning.pdf Meeting notes]
*January 12, 2011: Board of Supervisors approves proffer amendment allowing delay of construction of Meeting Street, but does not follow commission's recommendation on transit funding. <ref name="jan2011-proffers" /> [http://www.cvilletomorrow.org/docs/20110112-Hollymead-Rezoning.pdf Meeting notes]
*January 12, 2011: Board of Supervisors approves proffer amendment allowing delay of construction of Meeting Street, but does not follow commission's recommendation on transit funding. <ref name="jan2011-proffers" /> [http://www.cvilletomorrow.org/docs/20110112-Hollymead-Rezoning.pdf Meeting notes]

Revision as of 13:36, 11 October 2011


Logo-small25.jpg This article is a stub. You can help cvillepedia by expanding it.
A map depicting the many different sections at Hollymead Town Center

Hollymead Town Center is a mixed-use development located about seven miles north of Charlottesville along Route 29 North. As of 2011, while it consists of a shopping center with standard big box store tenants, plans to include residential units have been approved.

The developer, Wendell Wood, received approval for Hollymead Town Center from the Albemarle County Board of Supervisors in July of 2003[1]. Since then, other sections of the town center have been rezoned, each under different zoning categories.

Potential residential build-out

Hollymead Town Center Area C has a total capacity of 120 dwelling units and 34 have been built. [2]


Timeline

  • August 6, 2003: Board of Supervisors approves rezoning. [2]
  • January 11, 2011: Albemarle Planning Commission recommends amendment of proffers to change required timing of construction of Meeting Street. Also recommends halving of amount developer must contribute towards transit. [3] Meeting notes
  • January 12, 2011: Board of Supervisors approves proffer amendment allowing delay of construction of Meeting Street, but does not follow commission's recommendation on transit funding. [3] Meeting notes
  • March 10, 2011: 90,000 square foot Kohl's department store opens. [4] Wood tells the Daily Progress that he has other tenants lined up and the center will soon be at 90% capacity.

References

  1. http://cvilletomorrow.typepad.com/charlottesville_tomorrow_/2006/09/htcproffers.html Charlottesville Tomorrow, 8 Jan 2009
  2. 2.0 2.1 Web. [http://www.albemarle.org/upload/images/forms_center/departments/community_development/forms/PC_Reports/COMP_PLAN_UPDATED_10-11_STAFF_REPORT3.pdf CPA 2013-00001 COMPREHENSIVE PLAN REVISION Part 2: Trends], Table 6: Residential Units Approved through Rezonings and Special Use Permits, County of Albemarle, September 28, 2011, retrieved October 11, 2011.
  3. 3.0 3.1 Web. New Kohl’s store still on schedule after Hollymead proffer amendment, Sean Tubbs, Charlottesville Tomorrow, January 13, 2011, retrieved February 1, 2011.
  4. Web. Kohl's continues U.S. 29 growth, Daily Progress, Lee Enterprises, retrieved March 11, 2011.